Following several personnel changes affecting various stages of the rebuild process, we have some recent advancement.
Engineers Harrison Grierson now have a staff working full time on the project (as of last Friday). The detailed design work is around 80% completed, and the draft layouts are aimed to be ready by next Wednesday.
These then go to comment by the project architect (Greg Young) and Heritage, prior to the final structural documentation being prepared for scoping and costing.
Meanwhile the architects have completed the information capture for all of the flats, required for them to prepare a set of as-built plans. And AANZ have completed their assessment and sampling for asbestos in all 8 flats.
Next update due at the end of next week.